Excavation starts. View towards the east. 8 views
|
|

Footings for support building. 5 views
|
|

Foundation walls for support building started. 5 views
|
|

Instrument Room #1: foundation work for walls starts. Vertical fiberglass rebar seen. 7 views
|
|

Completed foundation for the walls for one instrument lab and its control room. 7 views
|
|

Detail showing vertical fiberglass rebar for instrument room walls and epoxy-coated rebar for exterior walls. 6 views
|
|

Detail showing buttresses supporting interior foundation walls. 7 views
|
|

All foundation walls fininshed. Neoprene sheets on interior of instrument rooms' foundation walls. 7 views
|
|

Neoprene sheets on the inside of instrument room foundations & PVC pipes for Helmholtz coils.9 views
|
|

Detail of instrument room reinforcement using fiberglass rods. 10 views
|
|

Detail of instrument room reinforcement using SS316 rods. 12 views
|
|

Reinforcement added to Instrument Rooms prior to pouring concrete for slabs. 11 views
|
|
|
|